1. Development of algorithms, technical and operational documentation and consultation in the part of the process control system of the 52 MW steam-gas power plant for ENERGY-ORGRES EOOD (Bulgaria)
2. Modernization of the control system when equipping unit №1 of Zaporizhzhya TPP with a pipeline to start the feed turbopump from a third-party source
3. Changing the configuration of cabinets of the software and hardware complex of the monitoring system of Zaporizhzhya TPP power units
4. Commissioning works to expand the monitoring system of power units of Burshtyn TPP
5. Maintenance and repair of monitoring and control systems of power units st. No. 7, 9 Burshtynska TPP
6. Correction and adjustment of parameters of the main automatic control systems of the power unit st. No. 1 of Zaporizhzhya TPP
7. Modernization of the control system for the performance of feed electric pumps with the help of hydraulic couplings of unit No. 2 of Kharkiv TPP 5