Certificate for the management system according to ДСТУ ISO 9001:2009 №UA2.171.09129-15
Zmiiv TPP, power unit 6.
A trial run of the unit was conducted at the transfer of coal gas to the gas group.

Zaporizhzhya NPP, power unit 1.
Issue report on tests at the beginning of the fuel company RU regarding the possibility of participation of units in the NPRCH in the UES of Ukr...
Zaporizhzhya NPP, power unit 1. Complex tests on the capacity of 81% Nnom at the beginning of the fuel company RU regarding the possibility of the participation of units in the NPRCH in the UES of Ukraine
Kharkiv TPP-5. Block 2. Completed NDP CCM.
Moldavian DRES. Work on the design of the modernization of the CCM of power units N11, 12.
Kharkiv TPP5 has begun. The supply of cabinets for the SDC CC.2 is completed.
LCME "Lvivteploenergo", CHP-1. The project of automation of steam boiler №8 was developed.
DTEK Burshtynskaya TPP Unit 7. Service maintenance of CCM has been carried out.
LLC "EMV-ENERGO" has passed the certification of quality management system to meet the requirements of DSTU ISO9001: 2015 "Quality Management Systems. Requirements »
Kharkiv TPP-5 block number 2. Development of a working project on replacing power cabinets and assemblies of the RZPO of th...
NNEGC, Zaporizhzhya NPP, block number 1. Conducting research at several levels of the load of the power unit at the end of the fuel company RU.
DTEK Pridneprovskaya TPP, block number 9. The project of joining the PTC CCM unit with the new PTC (Emerson) CCM pylostems when transferring the ...
Zmiiv TPP, block number 6. Beginning of the work on technical re-equipment of the boiler unit for combustion of coal in the gas group in the CCM.
Kharkiv TPP-5 block number 2. Supply of CCM equipment.
DTEK Burshtynskaya TPP, block number 11. Providing services for the installation of auxiliary equipment and control systems for the frequency control of helicopters and fuel regulator.
Employees of LLC "EMV-ENERGO" have increased their qualification in the direction of engineering-building design in terms of maintenance, noise protection and received certificates from the NGO "Guild of Designers in Construction".
NNEGC, Zaporizhzhya NPP. Development of a program for con...
Zmiyiv TPP. 200 MW units No 1-6. DCS project development, design and implementation to calculate the technician-economic indicators as well registration units events emergency have been completed.
Lviv TPP-1, boiler No.6. Microprocessors regulators implementation have been completed.
Zmiyiv TPP. 200 MW unit No 5. DCS project development, design and implementation for new systems of filing of pulverized coal in the furnace of the boiler have been completed.
Zmiyiv TPP, Prydniprovsk TPP, Kharkiv TPP-5. Continuation of the implementation of power units digital control systems.
Kharkiv TPP-5. 100 MW unit No 1. The new digital electro-hydraulic system of turbine was implemented.
Zmiyiv TPP. 200 MW units No 1-6. DCS project development, design and implementation to calculate the technician-economic indicators as well registration units emergency events.
Zmiyiv TPP. 200 MW units, boiler No 2. DCS project development, design and implementation for new systems of filing of pulverized coal in the furnace of the boiler have been completed.
Prydniprovska TPP, 150 MW units, boilers No 7-8. DCS project development, design and implementation for new systems of filing of pulverized coal in the furnace of the boiler have been started.
LLC "EMV-ENERGO" quality management system successfully passed the supervision audit for complains with standard DSTU ISO 9001:2009.
Lviv TPP-1, boiler No.6. Microprocessors regulators implementation have been started.
News
Projects have been developed: «Technical re-equipment of DTEK ZAPORIZHSKA TPP power unit control system №2» and «Technical re-equipment of DTEK ZAPORIZHSKA TPP power unit control system system №4»
1. Development of algorithms, technical and operational documentation and consultation in the part of the process control system of the 52 MW steam-gas power plant for ENERGY-ORGRES EOOD (Bulgaria)
2. Modernization of the control system when equipping unit №1 of Zaporizhzhya TPP with a pi...
1. Received a European certificate for the manufacture of electrical switchboard products.
2. Assembly and delivery of distribution cabinets and CB for PureCannabiSwiss AG.